Matrix completes the BG Tunisia Miskar Offshore Process Terminals Electronic Safety Case ahead of schedule.

Sept 2014

Building on the successful completion of BG’s Tunisia's Hasdrubal NUI Electronic Safety Case (ESC) in 2013, Matrix is pleased to announce a follow-up success in the completion BG Tunisia’s Miskar Complex ESC. This project had a planned duration of eight months but was completed in seven; one month ahead of schedule. Project Lead, Cecile Petit said: “We are particularly pleased with the completion of this project ahead of schedule as it covered not one but three offshore platforms including Production, Living Quarters and Flaring. For us this demonstrates why we are the market leaders in electronic safety cases"